Analysis of Time Overrun in Road Upgrading Projects under Infrastructure Development Office
Kanchanpur District, Nepal
Student: Birendra Singh Badal
Supervisor: Prof. Dr. Thusitha Chandani Shahi
Submitted Date:
June, 2023
Abstract
Road construction projects are the key infrastructural development backbone for providing
access to overall development activities. The time overrun in road construction projects pose
a significant challenge for stakeholders and constructing parties, as they lead to the cost
overrun and increase overhead costs for contractors. The projects that progress on the
completion of the road construction project get halted due to the time overrun of road
construction and all beneficiaries become deprived of the opportunity for a longer time
through the efficient use of the smooth road. The main objectives of this study were to
identify the factors of time overrun and the impacts caused by time overrun and then to
recommend strategies to minimize time overrun.
A questionnaire survey with 62 respondents were conducted to identify the major factors
affecting time overrun and to assess the impact caused by time overrun in road upgrading
projects. The questionnaire responses were analyzed using the relative importance index
(RII) method and Spearman’s rank correlation coefficient. The case study was conducted
on eleven selected projects to identify the factors contributing to time overrun and their
impacts on the projects. Key informant interviews were conducted with experienced road
project experts to identify the preventive measures to minimize the time overrun.
Cronbach’s alpha was used to test for reliability and internal consistency of the
questionnaire.
It is found that 9.44%, to 256.76% of the project duration exceeded in the projects. The
results indicated that road right of way related issues, shortage of materials, financial
difficulties faced by contractors, delay in site resources mobilization, poor site management
and supervision, use of old/improper construction method and equipment, weather effect on
construction activities, force majeure events (like Covid pandemic) and abnormally low bids
by the contractor were the most significant factors contributing to time overrun. The results
also show that extension of completion time of the project, escalation of material price,
difficulties for public users, negative social impact, and Increase in overhead expenses were
the most impactful consequences of time overrun on road upgrading projects. The findings
also suggest the most recommended strategies to minimize or control the time overrun.
viii
These strategies include conducting detailed site investigations, thoroughly reviewing of
designs, drawings, and plans before the tendering stage, adequate planning and management
by all involved parties prior to commencing work, develop a mechanism selecting
technically competent and experienced contractor with sufficient resources, set realistic
timeframe, ensure quick decision making and designing of the project with experienced and
knowledgeable personnel in road projects.
Keywords
Time overrun, impact, Major factors, Relative importance index