NOTICES

THESIS ABSTRACT

Risk Assessment in Selected Hydropower Projects of Nepal under Engineering, Procurement and Construction Contracts

Risk Assessment in Selected Hydropower Projects of Nepal under Engineering, Procurement and Construction Contracts

Student: Tikaram Niroula

Supervisor: Er. Gyaanendra Prasad Kayastha

Submitted Date: May, 2022

Abstract

Risk is the combination of the likelihood for a certain problem to occur (an unwanted situation) with the corresponding value (impact) of the damage caused. Project risk can be defined as “An uncertain event that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, quality, or scope.” Risk assessment only includes the identification, evaluation and ranking of the risks and is the subset of risk management. Risk management is a systematic process that includes risk assessment analyzing and responding to the risks. This research primarily focus on the risk assessment and also studies the possible risk management measures through risk allocation and other measures. The objective of this study are “to identify the risks of Hydropower projects in Nepal under Engineering, Procurement and Construction Contracts”, “to identify the major risks based on probability, impact and risk score in hydropower projects under EPC contracts in Nepal”, and “to suggest the possible risk management measures for hydropower projects in Nepal under EPC contracts”. To achieve the objectives of this research, the list of risks has been identified from the review of various literatures and has been verified with the experts of relevant fields in connection with the preparation of questionnaire. The questionnaire survey has been carried out to find the probability and impacts of each risks and the significance of proposed risk management measures using 5 scale Likert’s Scale. The questionnaires were sent to the professionals from Employer, Contractor and Consultant of selected hydropower projects. The set of questionnaire was sent to 74 respondents of 4 projects and response from 62 respondents was received but only 60 responses were found to be valid. The significance of risks have been calculated as the product of probability and impact of the risks and the risks has been ranked as per the level of significance of risks. For ranking of the risks as per their significance, the Relative Importance Index (RII) has been used for defining the overall risk score and risk rank. The significance of possible risk management measures were evaluated from questionnaire survey using the RII technique. As a part of risk management measure, the Key Informant vi Interview (KII) was done to find the risk allocation to Employer, Contractor, shared risks and transferred risks. The relative importance index of each risk along group and overall RII was calculated, ranked to find the correlation between the different ways and the testing of hypothesis was done to find out the significance of correlation. The major 46 risks grouped into 9 groups were identified and those risks were used for further study of their significance. The total risk score was calculated as the product of probability and impact. The most significant risks identified were “risk of subsurface geology”, force majeure” and “construction delays. From the study it was found that the major risks have been shared by the parties and one has been transferred to other party as risk management measures. The other most significant risk management measures identified were “preparation of contract documents by highly experienced personnel”, “competent project management team” and “conduct sufficient investigations and feasibility before procurement”. This study has recommended to work out on the detailed risk management of projects before project formulation and minimizing the unforeseeable risks and the risks of subsurface geology should be taken by the Employer.

Keywords

Risk assessment, Risk management, Hydropower, Engineering, Procurement and Construction (EPC) Contracts