Assessment of Delay in Underground Electrical
Cabling Projects in Kathmandu Valley under
Nepal Electricity Authority, Nepal
Student: Amir Shrestha
Supervisor: Asso. Prof. Hari Mohan Shrestha
Submitted Date:
February, 2024
Abstract
Electric power is the backbone of any developing country. The power sector has mainly
three components: power generation, power transmission and power distribution. Power
distribution plays a vital role in supply of electricity to consumers. Electricity is considered
one of the basic utility and adequate and reliable power is necessary. Construction of
underground electricity distribution reduces losses and increase reliability also.
In this study, a total of four under-construction underground electrical cabling projects were
selected for finding delay in the construction, its causes, effects and remedial measures. The
questionnaire survey, Key Informant Interview (KII) and project documents were used to
collect data for this study. The questionnaire were developed based on the literature review,
discussion with the project team to investigate the content validity in line with the research
objectives. Hard copy questionnaire were distributed to clients, consultants and contractors
representatives and collected. The relative importance index (RII) method was used to
calculate the rank of delay factors. According to the ranking of RII, the major factors of
delay were delay in approval from other agencies, traffic interruption, covid pandemic, local
people intervention, and delay in site handover.
It was found that the major effects of delay of underground electrical cabling projects were
time overrun, cost overrun, dispute, arbitration and litigation.
In order to reduce the construction delay, the client has to obtain permissions and approval
of concerned agencies/departments before award of the contract, have regulatory
arrangements between interdepartmental bodies, coordination, carry out exiting utility
survey mapping along with topographical survey, proper supervision, qualified contractor
should be hired and proper planning with spoil management, traffic management,
reconstruction of road should be carried out.
Keywords
Underground electric cabling, spoil management, traffic management,
time overrun, cost overrun, Remedial measures