Delays in Selected National Pride Road Construction
Projects of Nepal
Student: Prabin Jung Thapa
Supervisor: Er. Rajesh Khadka
Submitted Date:
January, 2024
Abstract
Infrastructure projects play an important role in the economic prosperity of a country. Among
many infrastructure projects, transport infrastructure plays a basic and paramount role in
enhancing mobility of people and goods thereby increasing the efficiency of a nation’s
advancement towards prosperity. Nepal’s geology comprises mostly hills and mountains with
only a small covered plain land mass which significantly increases the value and the importance
of better connectivity via road networks. Nepal has been striving to improve its land connectivity
since the commencement of the first development plan in 1956 AD. However, due to a shortage
of adequate funding, a lack of proper project administration and management, along with poor
road quality has crippled Nepal’s goal of accelerated infrastructure development. The purpose of
this study is to assess the cause and effect of delayed development effort initiatives in road
transportation infrastructures categorized as ‘National Pride Projects’ by the Government of
Nepal and present remedial measures to address pertinent delay factors for planned project
execution.
This research is based on primary data with a qualitative and quantitative design approach. In
this research, the population is considered as the sample size, and transport stakeholders familiar
with their involvement in road construction are considered as respondents. The questionnaire
was prepared to take into consideration of major project stakeholders, viz. Client, Consultant,
and Contractor. Out of distributed 114 nos. of questionnaires, 91 nos. of responses were received
– each with unique input responses thus aiding in the preparation of this research’s findings. The
Primary Data comprised a Questionnaire Survey that was further tabulated by “Relative
Importance Index’ methodology for Delay Cause Factors. Similarly, for the analysis of effects of
project delays, out of a structured questionnaire, the Principal Component Analysis (PCA)
Statistical tool was used, and Key Informant Interview (KII) methodology was conducted in
identifying remedial measures for the study projects.
Te study found by the RII method, that low bids, delay in tree cutting and utility relocation
permits, longer period of approval of IEE and EIA documents, lack of good coordination mong
vi
government bodies, and delay in land acquisition by the client were top factors contributing to
delays. Accordingly, the application of the Principal Component Analysis (PCA) method in the
identification of delays effects subsequently found primarily, variation in Time and Cost
followed by Claims and Disputes, Failure of project objectives, Legal Complications of contract
termination, profit loss, Increased Financial burden and poor quality as main determinants if
effects of project delays. The KII method collecting The PCA study conducted found that
variation in cost and times affecting the project objectives are two major effects of project delay
effects followed by reputational loss, increased budget and poor quality. The study found out low
bids, delay in tree cutting and utility relocation permits, longer period of approval of IEE and
EIA documents, lack of good coordination among government bodies, and delay in timely site
acquisition by the client.
The study is primarily focused into causes of project delays thereby understanding the effects
that have been caused with expert opinion on the remedial measures based on inputs collected
from the survey and analysis respectively. The research focused into the important role of
transport infrastructure in Nepal's economic progress, highlighting the challenges hindering its
development.
Keywords
Road Construction Project, Construction Delays, Relative Importance Index,
Principle Component Analysis