Abstract
Nepal lies in an active seismic belt. The history is full of devastating earthquakes. The
earthquake risk in Nepal is believed to be one of the highest in the world. For safer and
reliable construction of buildings all federal, provincial and local levels have legal
obligation to implement Nepal National Building Code. However, the newly formed
municipalities and especially Rural Municipalities face challenges in enforcing building
codes.
The objective of this study is to determine the Compliance of Building Code in
Construction of Residential Buildings in Sisne Rural Municipality, Rukum (East) District,
to determine the characteristics, awareness and experience of masons involved in building
construction and to determine the reasons behind the non-compliance of building code in
construction and their probable solutions to overcome. The methodology involved was field
observation along with checklist survey, questionnaire surveys, and KII.
The study showed that the out of 27 constructed buildings only one building was comply
with the checklist of compliance and remaining buildings are not complied. Similarly, out
of 13 under construction buildings, none of the buildings are comply as per the compliance
checklist. Various parameters like changes in plinth area, size of room, change in depth of
beam and change in size and position of staircase have been altered than approved design
and drawings. Similarly, lapping of column rebar, lapping of beam rebar are major lacking
in under construction buildings. There is a lack of sufficient awareness levels of the masons
on basic concept behind the complaince of the building code working in the construction
buildigs. Majority of mason’s perspective for the reasons behind non-compliance of
building code is due to instructions from owner during construction. Masons too alter the
drawings to make easy in construction violating the compliance requirement.
Lastly, it has been found that the major reasons behind non-compliance in construction are
due to lack of awareness of general public and house owner on code compliance as this is
very new subject to them, lack of sufficient training to technical manpower in the
municipality for timely and frequent supervision, lack of availability of trained masons and
contractor in Sisne Rural Municipality, lack of effective process of building permit and
standard operating procedures for controlling code compliance during construction, lack of
coordination between the house owner, designer and masons involved in construction,
misconception of the house owner that the compliance of code will increase the cost of the
viii
building, lack of sufficient practical knowledge among sub-engineers and lack of stringent
monitoring and supervision and disbelief of house owners.
The study recommends the probable solutions to overcome the problems of non-
compliance as conduction of mass awareness programme on need of earthquake resistant
design and application of building code for the general public and house owner, sufficient
training to their in-house technical personnel, municipality should start to train the available
mason in Sisne Rural Municipality, prepare and enact standard operating procedures for
effective building permit process to enhance the code compliance during construction,
introducing three party agreement processes between the owner, designer and mason
involved in the construction for better coordination, prepare and enact effective reward and
punishment system for compliance and non-compliance through stringent monitoring and
supervision during construction.
Keywords
Building Code, Compliance, Rural Municipality, Awareness,