Assessment of Time Duration Estimation Models for Design-Build and Design-Bid-Build Bridge Projects under Department of Roads
Student: Mukunda Kumar Karn
Supervisor: Er. Parikshit Kadariaya
Submitted Date:
August, 2026
Abstract
For a construction project to be successful, it is essential to prepare a realistic contract
estimate and assign a practical contract duration. This study aims to perform assessment of the
time duration estimation models for Design–Build and Design–Bid–Build procurement
methods for bridge construction projects implemented under the Department of Roads. A
Sequential Explanatory Mixed Methods Design methodology is adopted using data collected
from 40 completed bridge projects executed between Fiscal Year 2018/19 and 2023/24,
comprising 20 DB projects and 20 DBB projects. Contract documents, completion reports,
Extension of Time (EoT) records, Variation Orders, and Key Informant Interviews with
professionals served as data sources for this research.
The study employed descriptive statistical analysis, time duration estimation using DoR
contract duration estimation guidelines and Bromilow’s Time-Cost modelling of bridge
projects procured under DB and DBB approaches. DB projects demonstrated comparatively
better schedule and cost performance, with an average time overrun of 41.10% compared to
132.10% for DBB projects. Similarly, DB projects achieved slight cost savings of 0.39%,
whereas DBB projects experienced an average cost overrun of 5.33%. Current DoR duration
guidelines systematically underestimated completion times for both delivery systems. BTC
regression models also yielded low goodness-of-fit and substantial predictive errors; MAPE
value for DB and DBB contracts being 39.07% and 49.66% respectively. The regression cost
sensitivity coefficient () for DBB contracts was nearly three times that of DB contracts.
The results suggested that existing duration estimation guidelines and single-variable models
failed to capture the complex risks inherent to bridge construction in Nepal. Replacing cost-
only estimation models with Multiple Linear Regression, adopting a structured Procurement
Selection Decision Matrix and revision of existing duration estimation models were suggested
to improve fast track delivery and efficient resource utilization. Factors beyond procurement
method that influence project performance require further research. The findings of this
research may assist policymakers, procurement agencies, and construction professionals in
selecting appropriate procurement methods for future infrastructure projects.
Keywords
Design–Build, Design–Bid–Build, Time Duration Estimate, DoR Guidelines, BTC Modelling, Bridge Construction, Procurement Practices, Construction Management