Factors Causing Design Changes During Construction Stage in Selected Government Building Projects Under Office of Federal Urban Development and Building Construction, Kathmandu Division.

Factors Causing Design Changes During Construction Stage in Selected Government Building Projects Under Office of Federal Urban Development and Building Construction, Kathmandu Division.

Student: Luniva Shakya

Supervisor: Dr. Dinesh Sukamani

Submitted Date: August, 2026

Abstract

Changes in design during the construction phase are one of the common problems in building projects that cause cost overruns, delays, rework, decreased productivity, and conflicts between project parties. This research is concerned about factors that influence design change during the construction phase in some selected government building projects in the FUDBC Kathmandu Division. It attempts to find out the causes for the occurrence of design change, effects of design change in the performance of the projects, and ways to minimize it. In this research, a combination of qualitative and quantitative research approaches has been used, which include questionnaire survey of clients, consultants, and contractors, key informant interviews of the experienced individuals in the field of client, consultant and contractor, and case studies of the selected projects. Data were analyzed using the Relative Importance Index (RII), Spearman correlation, Principal component analysis (PCA), and descriptive statistical techniques. As per the findings of the research, the design changes are caused mainly by the top three factors including Inadequate Design and Site Investigation (DS), Planning & Coordination Deficiencies (PC) and Construction phase Constraints (CC) where Inadequate Design and Site Investigation is the most significant one with the variance of 27.507%. Variance of other determinants is 19.617% and 10.364%. The top factor Inadequate Design and Site Investigation (DS) includes three causes like Change in design when construction starts before the design is final or when design and construction happen simultaneously (0.921), Differing site conditions (e.g. unexpected rock layers, loose soil, high water) (0.906) and Lack of proper site investigation including inadequate site area surveys (0.915). There are other causes like error and omissions in design, lack of coordination between stakeholders, the failure of a consultant to provide adequate and clear information in the tender documents, errors, and omission of consultants. Additionally, the study finds out that the design changes have negative effects on the project performance by causing time delays with RII (0.850) cost overruns with RII (0.837) and work on hold with RII (0.804). The least RII score is 0.508 from the quality impact, meaning that despite the XI design change that happened, the quality of the construction of the buildings was not affected. In addition to the negative effect of design change, the positive aspect of design change has been ranked in the improvement of functional performance of building with RII of 0.806 as the top positive effect of design change. It becomes evident from the research that even though it is impossible to stop the occurrence of changes during design phase, but their occurrence can be significantly reduced by proper planning at the time of design phase including ensuring proper review of the design, proper investigation of the site and soil, proper coordination between project participants, interdisciplinary review of drawings, and proper understanding of client’s requirements.

Keywords

Design Change, Construction Stage, Government Building Projects, FUDBC Kathmandu Division, Principal component analysis (PCA), Remedial measures, Negative and Positive impacts.