Client’s Perception of Contractors’ Performance in Residential Building Construction: A Case Study of Bharatpur Metropolitan City.
Student: Manish Adhikari
Supervisor: Dr. Dinesh Sukamani & Asst. Prof. Manoj Kuwar
Submitted Date:
August, 2026
Abstract
The rapid urbanization of city areas has led to many people becoming involved in the
construction sector in Nepal, leading to serious issues of client satisfaction as most
residential construction is still informal. Poor workmanship, time overruns, and cost
escalations are common, with little to no training for workers. This has caused many
clients to distrust the construction capability of local contractors, fueled by poor
supervision and monitoring by local government.
This research identifies the major reasons of dissatisfaction among clients on
contractors' performance in Bharatpur Metropolitan City (BMC) and suggests
possible strategies to the stakeholders involved, including contractors, clients and
government entities responsible for the approval, monitoring and evaluation of
residential construction works.
Data was collected from 357 residential clients through a structured questionnaire.
The study identifies the underlying factors of clients' satisfaction through Principal
Component Analysis (PCA), which reduced the survey items into six underlying
components of clients' perception. Multiple regression was then used to assess the
impact of these components on overall satisfaction, explaining 62.7% of the variance
(R² = 0.627). Based on these findings, performance gaps were identified: high beta
and low perception score were considered critical areas for intervention, triangulated
with open ended client feedback and Key Informant Interview (KII) suggestions.
The findings show that contractors of BMC excelled in relational traits like
Communication and Accountability, and Professionalism and Site Management, and
maintained baseline in Quality and Performance Assurance and Site Efficiency and
Technical Oversight. However, they were found lacking significantly on Schedule and
Time Predictability and Technology Adoption and Safety Practices, covering timely
completion, schedule adherence, site safety, wastage control, supervision, and
adoption of modern technology.
It was recommended that contractors address these gaps by using a minimum toolkit
instead of costly equipment, enforcing use of PPE, maintaining a material log book,
and appointing a regular supervisor. Clients were recommended to assess a
contractor's equipment, experience, and past performance before hiring, and integrate
2
a milestone-based timeline into the contract. It was suggested that BMC enforce its
current supervision-agreement provision strictly, license contractors according to their
experience and capacity, and require a three-party scheduling and safety agreement
during the drawing approval.
These findings aim to bridge the gap between contractor execution and client
expectations, contributing toward a more accountable residential construction practice
within Bharatpur Metropolitan City.
Keywords
Client satisfaction, Contractor performance, Residential construction; Principal Component Analysis, Bharatpur Metropolitan City