Analysis of Causes and Effects of Delay in
Retrofitting in High-rise Building: A Case
Study of Park View Horizon, Kathmandu
Student: Rabindra Shrestha
Supervisor: Er. Sujan Nepal
Submitted Date:
February, 2024
Abstract
Retrofitting projects in high-rise buildings present unique challenges, often leading to delays
that can significantly impact project timelines and costs. This study investigates the primary
factors causing delays in retrofitting projects, aiming to provide insights into effective
mitigation strategies. Utilizing a combination of qualitative and quantitative research
methods, data was collected through questionnaires and Key Informant Interviews (KIIs) from
stakeholders involved in the Park View Horizon project located in Kathmandu, Nepal. The
Relative Importance Index (RII) was employed to assess the significance of various factors,
revealing communication gaps, inconsistent decision-making, and ineffective problem
resolution as prominent concerns across stakeholders. Additionally, the Spearman rank
correlation coefficient demonstrated strong agreement between Overall and Consultant
perspectives, affirming the reliability of the findings.
Furthermore, the investigation into the effects of delays in retrofitting highlighted time and
cost overruns as primary consequences, with a notable correlation between perspectives.
Enhanced stakeholder collaboration, clear communication channels, and proactive risk
management emerged as key recommendations to mitigate delays effectively. Thematic
analysis of Key Informant Interviews (KIIs) provided nuanced insights into specific
challenges encountered in retrofitting projects and effective mitigation strategies,
emphasizing the importance of early engagement with regulatory authorities and leveraging
advanced technologies like Building Information Modeling (BIM).
Moreover, secondary data analysis of historical records, project documentation, and literature
review complemented the primary findings, enriching the understanding of retrofitting
challenges and mitigation approaches. The use of statistical tools such as SPSS for reliability
testing and Python for thematic analysis enhanced the rigor and depth of the study.
In conclusion, the study underscores the critical need for proactive measures to address
communication gaps, streamline decision-making processes, and enhance stakeholder
collaboration to mitigate delays effectively in retrofitting projects.
Keywords
Retrofitting, High-rise buildings, Delay mitigation, Stakeholder collaboration,
Communication gaps