THESIS ABSTRACT

Causes, Impacts and Preventive Measures of Variation Order in Selected Building Projects of Central Level Project Implementation Unit (Building and Housing) in Kathmandu District.

Causes, Impacts and Preventive Measures of Variation Order in Selected Building Projects of Central Level Project Implementation Unit (Building and Housing) in Kathmandu District.

Student: Gopal Bhattarai

Supervisor: Dr. Dinesh Sukamani

Submitted Date: February, 2024

Abstract

Variation orders consist of the additions, omissions, alterations and substitution in terms of quality, quantity and schedule of works. Central Level Project Implementation Unit (Building and Housing) CLPIU(BH) is responsible to reconstruct public buildings, private housing and heritage buildings is facing variation as one of the serious issues. Variation orders impacted the project performance, procurement delay, quality degradation, disputes among professionals, decline in firm reputations, increase in overhead expenses etc in projects of CLPIU(BH). But there have been few researches carried out about cause and impact of variation order in road, school building and hydropower projects of Nepal. However, no research work has been carried out about variations orders in the building projects under CLPIU(BH). So, this research aims to highlight causes and impact of Variation Order in selected Building Projects of CLPIU(BH) as well as to suggest preventive measures to reduce the variation orders in similar building construction projects. For this purpose, 11 construction projects of CLPIU(BH) were considered. Questionnaires for Causes, and Impacts of Variation Order in Selected Building Projects of CLPIU(BH) in Kathmandu district were provided to potential respondents 110 i.e., client, consultant and contractor through the goggle forms and emails. Among 110 questionnaires, 81.81% i.e., 90 questionnaires respond were received. Data were analyzed using MS Excel, RII and PCA by SPSS. KII conducted to identify preventive measures to reduce variation order in building construction projects in future. For causes of variation order in Selected Building Projects of CLPIU(BH), RII was used. The major client related causes are change in plan and scope, lack of proper review of design and estimate provided by consultant, adaptation of new technologies, increase in client requirements and insufficient coordination between various departments. The major contractor related causes are poor project planning and management, inadequate study of tender documents, intention of contractor to substitute new items to maximize profit, inadequate proper communication with stakeholders and unfamiliarity with complex design of retrofitting technology. Also, major consultant related causes are shortcoming in design viii with respect to site condition, flaws in BOQ and estimate prepared by consultant, inadequate study of availability and requirements of materials and equipment, not providing required documents and detailing to contractors and negligence in supervision PCA approach was used to identify impacts of variation order in selected building projects of CLPIU(BH). Result have shown that impacts of variation order were divided into 6 components i.e., cost fluctuation, difficulty in project management, complexity to beneficiaries, delay in project progress, difficulty in fixation of new rate and erosion of professional integrity. Fixing needs before finalization of estimate, hiring expert to design and supervision, forming coordination mechanism between government bodies, involving contractor in design phase, ensuring proper study of site condition and maintaining proper communication and coordination were identified preventive measures to reduce the variation orders in similar building construction projects in future obtained from KII. Thus, variation order is common in construction projects of CLPIU(BH). Variation order caused project delay ranging from 3.5 months to 27.73 months and cost rise from 4.12% to 24.94% in studied selected building projects of CLPIU(BH) in Kathmandu district.

Keywords

Building Projects, Variation Order, Principal Component Analysis, Relative Importance Index